• ZINARA collected US$469.3 million in 2025, up 28%, as major road rehabilitation missed its target
  • Harare to Chirundu's US$2.53 million per kilometre exceeds Zambia's US$1.99 million indicative corridor cost
  • African comparisons expose differences in project pricing, while ZINARA's administrative costs exceeded the reported statutory ceiling

Harare- Zimbabwe's road financing system collected US$469.3 million in 2025, equivalent to US$39.1 million monthly, while the country's road rehabilitation programme delivered only 58% of its major works target. The financing challenge becomes more consequential when measured against construction costs across Africa.

Zimbabwe's proposed US$900 million Harare to Chirundu project carries an indicative investment cost of US$2.53 million per kilometre, approximately 27% above Zambia's US$1.99 million for the Lusaka to Ndola corridor. Both projects include infrastructure beyond the principal carriageways, making the comparison useful for examining investment requirements, although insufficient to establish differences in construction efficiency. The central finding is that Zimbabwe's road financing capacity cannot be properly evaluated without establishing how project costs are structured and how effectively expenditure translates into durable infrastructure.

Under the Roads Act [Chapter 13:18], ZINARA's Road Fund is principally intended to finance maintenance of the existing road network. The legislation also provides mechanisms for certain approved road development activities. This distinction matters because the cost of constructing new highways cannot automatically be used as a measure of ZINARA's performance in financing road maintenance.

According to figures presented to Parliament by ZINARA chief executive Nkosinathi Ncube, revenue increased approximately 28% from US$366.95 million in 2024 to US$469.3 million in 2025. Initial reported disbursements amounted to US$341.8 million, equivalent to 72.8% of collections, while a subsequent disclosure placed the figure at approximately US$361.3 million. The difference requires reconciliation against the authority's audited financial statements.

ZINARA generates revenue through tolling, vehicle licensing, fuel levies and other road user charges. Its 29 toll plazas reportedly collect approximately US$17 million monthly, implying US$204 million annually at that rate. The wider funding base supports a national road network estimated at between 87,654 and 97,000 kilometres, depending on classification.

Using the lower network estimate, annual collections represent approximately US$5,354 per kilometre. This measures the relationship between revenue and infrastructure coverage, not actual expenditure on individual roads. The comparison demonstrates how a substantial national funding pool can become limited when distributed across routine maintenance, resurfacing, reconstruction and existing financing obligations.

The construction economics provide a sharper perspective. Government's proposed Harare to Chirundu programme is estimated at US$900 million over 356 kilometres, implying US$2.53 million per kilometre. The investment includes rehabilitation and upgrading of the highway, modernisation of the Chirundu Border Post, toll plazas and weighbridges.

This is a corridor investment ratio rather than a verified pavement construction cost. Without a breakdown of the border post, engineering works, bridges, drainage and financing requirements, the calculation cannot establish the price of rehabilitating one kilometre of the highway itself.

Although ZINARA's principal mandate concerns road maintenance, major infrastructure projects increasingly involve financing arrangements supported by road user revenues. The proposed US$900 million Harare to Chirundu programme illustrates the relationship between infrastructure development costs and future revenue commitments. Comparing African construction costs therefore provides context for the country's wider financing requirements, while the assessment of ZINARA's statutory performance must remain grounded in maintenance expenditure and delivery.

Zambia offers a particularly relevant regional comparison. The Lusaka to Ndola dual carriageway project was awarded under a public private partnership valued at approximately US$650 million, covering a 327 kilometre corridor. Dividing the investment by that distance produces an indicative US$1.99 million per kilometre.

The Zambian project includes approximately 45 kilometres of additional road rehabilitation, 30 kilometres of bypasses, bridges, weighbridges and tolling facilities. The concession also incorporates financing and a 25 year arrangement, comprising three years of construction and 22 years of operation and maintenance.

Importantly, Zambia disclosed a more detailed financial breakdown of the investment. The original agreement allocated approximately US$577.4 million to construction, US$69.7 million to interest during construction and the remainder to other financing and working capital requirements. Using the principal corridor length, the construction allocation represents approximately US$1.77 million per kilometre, although that amount also covers the additional infrastructure within the contract.

This distinction strengthens the comparison with Zimbabwe. Zambia's publicly disclosed cost structure allows the construction component to be separated from financing expenses, while the Harare to Chirundu headline estimate does not provide an equivalent allocation. The difference limits any definitive conclusion about which project delivers construction at a lower cost.

Other Zambian roadworks have been priced considerably below the major corridor project. During a July 2025 parliamentary debate, the government reported that selected bituminous road contracts had been reduced from approximately US$1.2 million to around US$600,000 per kilometre. These figures concern different classes of works and were presented as government contract pricing, not an independently audited national average.

South Africa provides evidence that project complexity can substantially alter costs within one country. Reported South African National Roads Agency projects include the R56 Matatiele upgrade at approximately R30.8 million per kilometre and the R573 Moloto Road programme at R27 million per kilometre. Using an illustrative exchange rate of R16.50 per US dollar, these represent approximately US$1.87 million and US$1.64 million respectively.

A proposed 380 kilometre upgrade between Bela Bela and Beitbridge carries an estimated R10.8 billion budget, equivalent to approximately US$1.72 million per kilometre at the same exchange rate. More complex highway developments are substantially more expensive. The N7 upgrade has been reported at approximately US$5.31 million per kilometre, reflecting a different project scope.

The South African figures demonstrate why contract specifications must accompany cost comparisons. Widening, interchanges, bridge structures, traffic management and drainage requirements can produce materially different expenditure even where the underlying road lengths are similar. The dollar conversions are illustrative and should not be mistaken for audited US dollar project costs.

Kenya and Uganda provide further reference points. According to the Architectural Association of Kenya's 2025 built environment report, average expenditure on reported Kenya National Highways Authority works reached approximately KSh112.7 million per kilometre. At KSh129 per US dollar, this represents about US$874,000 per kilometre.

A 2024 International Monetary Fund technical assistance report used approximately US$716,000 per kilometre as a blended planning benchmark for Uganda. The estimate combined new construction, gravel road upgrading and rehabilitation, meaning it represents a planning assumption rather than the price of one comparable highway contract.

Historical World Bank research provides a broader African comparison. Its road construction cost study reported rehabilitation and reconstruction expenditure of approximately US$443,000 per kilometre in Ethiopia, US$298,000 in Ghana, US$318,000 in Mozambique and US$480,000 in Malawi. The study recorded approximately US$1.09 million in Kenya, while gravel to paved road upgrades averaged US$397,000 in Tanzania and US$479,000 in Uganda.

These observations originate from older contracts, principally reflected in research published in 2008, and have not been adjusted to 2026 purchasing power. Their relevance lies in demonstrating the historical variation across road categories, terrain, contracting markets and engineering requirements. They cannot establish current construction prices.

Zimbabwe's previous Plumtree to Mutare rehabilitation provides a domestic reference. The reported US$206.6 million investment across approximately 821 kilometres implies US$252,000 per kilometre. That programme involved different proportions of rehabilitation, widening and resealing, limiting direct comparability with major highway construction. Subsequent concerns over pavement deterioration also demonstrate why initial contract prices must be considered alongside durability.

The delivery record introduces a separate accountability measure. According to the 2026 National Budget, Zimbabwe's Emergency Road Rehabilitation Programme completed 69.55 kilometres of construction, reconstruction and rehabilitation during 2025 against a target of 120 kilometres. This represents approximately 58% of planned major works, leaving a shortfall of 50.45 kilometres.

Other interventions included 242.17 kilometres of resealing and overlays and 1,053.23 kilometres of gravelling and regravelling. ZINARA separately reported maintenance activities covering approximately 38,112 kilometres. These measures concern different engineering interventions and cannot be combined into one figure representing newly constructed roads.

The distinction is important because pothole repairs, drainage maintenance and pavement resealing have different costs and useful lives. Reported activity therefore needs to be assessed against expenditure by intervention type, with independent evidence of the condition of completed roads.

ZINARA's operating expenses add another financial dimension. At its October 2026 annual general meeting, the authority reportedly disclosed collection costs equivalent to 21% of revenue and administrative expenditure of 5.4%. Applied to 2025 collections, these ratios imply approximately US$98.6 million and US$25.3 million respectively.

The reported administrative ratio exceeded the stated statutory ceiling of 2.5%, creating an indicative gap of US$13.6 million at the year's revenue level. This calculation does not establish an immediately recoverable cash amount, since the underlying accounting classifications and statutory treatment require confirmation from audited records.

For perspective, US$13.6 million is equivalent to approximately 23 kilometres at Zambia's reported US$600,000 benchmark for selected bituminous roadworks, or about five kilometres at the indicative Harare to Chirundu corridor rate. The comparison illustrates the potential significance of administrative efficiency while recognising that the projects involve different construction requirements.

The financing arrangements also matter. Government has pursued a public private partnership structure for Harare to Chirundu, with CBZ linked to a US$100 million financing commitment associated with toll revenue. Such arrangements can accelerate infrastructure development, although future repayments create obligations against revenue that would otherwise support additional roadworks.

The African evidence establishes that Zimbabwe's proposed highway investment is above several reported regional benchmarks, while remaining below the cost of some complex South African projects. It does not provide a uniform construction rate against which the Harare to Chirundu contract can be conclusively judged.

Equity Axis takes the view that the most consequential gap is in project level disclosure. Zambia's separation of construction expenditure and financing costs demonstrates the information required to assess major infrastructure commitments. Zimbabwe's comparable disclosure should identify the amounts attributable to pavement works, bridges, border facilities, tolling infrastructure, contingencies, financing and project supervision.

The same approach should extend to completed roadworks, linking contract expenditure to engineering specifications, kilometres delivered and independently assessed pavement quality. ZINARA's revenue performance establishes the capacity to mobilise significant domestic funding. Government's construction statistics establish the physical outputs reported. A consistent relationship between these two sets of information is essential to determining value for money.

Zimbabwe's road financing performance must ultimately be assessed against the statutory purpose of the Road Fund, the maintenance delivered to road users and the cost of administering collections. The African construction benchmarks establish the financial demands of expanding the road network, while ZINARA's own expenditure and maintenance records provide the more direct measure of its institutional performance. The priority is a transparent reconciliation of the US$469.3 million collected, the resources allocated to road maintenance and the physical condition of the infrastructure those allocations were intended to preserve.