The project will probably be financed internally, said Debswana spokeswoman Matshidiso Kamona. She declined to comment on the expected costs or schedule. Debswana has received provisional approval from the Department of Environmental Affairs, pending public review of its environmental-management plan, the notice says.
Last year, then-Minerals Minister Sadique Kebonang said that government intended to include the financing of Cut 9 into its ongoing negotiations with De Beers for the renewal of the 10-year sales agreement covering output from the Debswana mines. The existing sales and marketing agreement ends in September 2020.
De Beers largely funded the Cut 8 project, which involved stripping 500 million tons of waste to expose an orebody containing an estimated 100 million carats that will be mined until 2024, when output is expected to start from Cut 9.
- Moneyweb
De Beers, Botswana to dig deeper at world’s richest diamond mine
By Respect Gwenzi, Apr 06, 2018
Debswana, the joint venture between Anglo American De Beers unit and Botswana’s government, is seeking permission to deepen the Jwaneng mine to 830 meters, according to a notice published in local newspapers Thursday. The Cut 9 project will extend the mine’s life by 11 years, to 2035, and allow the extraction of a further 50 million carats.
Jwaneng, which started full operations in 1982, is the world’s largest diamond producer by value and currently 650 meters deep. Cut 9 will involve stripping away waste at the bottom of the mine, both widening and deepening the pit. The previous extension project, Cut 8, cost about R35.8 billion and reached gem-bearing ore in 2016, seven years after work started.
The project will probably be financed internally, said Debswana spokeswoman Matshidiso Kamona. She declined to comment on the expected costs or schedule. Debswana has received provisional approval from the Department of Environmental Affairs, pending public review of its environmental-management plan, the notice says.
Last year, then-Minerals Minister Sadique Kebonang said that government intended to include the financing of Cut 9 into its ongoing negotiations with De Beers for the renewal of the 10-year sales agreement covering output from the Debswana mines. The existing sales and marketing agreement ends in September 2020.
De Beers largely funded the Cut 8 project, which involved stripping 500 million tons of waste to expose an orebody containing an estimated 100 million carats that will be mined until 2024, when output is expected to start from Cut 9.
- Moneyweb
The project will probably be financed internally, said Debswana spokeswoman Matshidiso Kamona. She declined to comment on the expected costs or schedule. Debswana has received provisional approval from the Department of Environmental Affairs, pending public review of its environmental-management plan, the notice says.
Last year, then-Minerals Minister Sadique Kebonang said that government intended to include the financing of Cut 9 into its ongoing negotiations with De Beers for the renewal of the 10-year sales agreement covering output from the Debswana mines. The existing sales and marketing agreement ends in September 2020.
De Beers largely funded the Cut 8 project, which involved stripping 500 million tons of waste to expose an orebody containing an estimated 100 million carats that will be mined until 2024, when output is expected to start from Cut 9.
- Moneyweb
Top Stories
Zimbabwe’s US$1.59bn Investment Pipeline Faces Execution Test: ZIDA Shifts Focus From Licences to Capital Deployment
Zimbabwe has approved almost US$1.59 billion of new investment proposals during the second quarter of 2026, although the more consequential number sits outside the licensing table. It is the amount of
1 hour agoAir Zimbabwe’s US$11m Loss Meets Growing Aviation Market: Passenger Growth Raises Return Hurdle on Fleet Renewal
One of the more revealing findings in the latest Auditor General report is that Air Zimbabwe can produce a clean set of accounts and still remain economically fragile. The Auditor General issued an un
4 hours agoGlobal Seas Hit 21.1°C Peak in August : East Africa Braces for Floods as Southern Africa Fears Drought
Global sea surface temperatures reached 21.1°C on 22 August 2026, the highest daily reading in Copernicus records dating to 1979. The new peak exceeded the previous 21.09°C record set in March 2024 a
14 hours ago