Zimplats parent in final stages of approving R10bn worth of new platinum projects

0
942

. Implats approving R10bn new platinum projects

. Projects to add 18 000z each

. Zimplats to produce 6.7 million tons

Harare – Platinum group metals (PGMs) mining and marketing company Implats, the parent company of Zimplats said it is now in the final stages of approving two exciting new platinum projects that will tick all the boxes of the company’s strategic intent.

Implats CEO Nico Muller made the announcement at a recent press briefing after the Johannesburg Stock Exchange-listed company reported a stellar set of financial results that recorded 328 percent rocketing headline earnings of R14.5 billion

The projects include Merensky reef expansion project at the Two Rivers platinum mine, an opencast mine in Steelpoort, Limpopo, and the other the expansion of the production capacity of the Bimha Mupani projects at Zimplats, in Zimbabwe.

The Two Rivers project will add 180 000 oz at a capital expenditure (capex) of R5.7-billion over the next four years and the Bimha Mupani expansion another 180 000 oz at a capex of R4.3-billion over the next four to five years.

“They’re both shallow, mechanised, low-risk and fit into our strategic objectives very well,” Muller said at a media briefing available on Mining Weekly.

Muller described the funding for the projects as being “very feasible within the current remit of our financial performance”, and added that the company hoped to come to the market within the next few months with announcements on both projects.

“We do believe that we have the most attractive opportunities within our own company,” Muller emphasised.

For some time now the Zimplats smelter has been operating at 6.5-million tons capacity a year from four mines and three concentrator plants.

Implats COO Gerhard Potgieter weighed in saying the expansion of Zimplats comes with a need for further beneficiation capacity.

He said a ramp of the proposed new Bimha Mupani mine expansion, it would become the fifth mine and together with the Bimha mine, will be growing into a significant size of the production.

“So much so, that this proposed project will take it to 6.7-million tons, which means that only those two mines together will be able to produce the full capacity of Zimplats, leaving the other three older mines with some excess capacity for us as they ramp down.

“So, the first thing we have to do is to provide a fourth concentrator unit at the operation, so that we can concentrate those tons. Unfortunately, the smelter at Zimplats is at full capacity, which means that the first step from that would be those concentrates having to come to our Rustenburg operations and be treated here.

“Longer term, we’ve acknowledged the fact that we are constrained as far as our smelting capacity in Zimbabwe is concerned, and we are busy with studies for a further furnace and the sulphur abatement that goes with it. It’s quite a substantial capital investment to be made and we’ve started with the feasibility studies on that. It’s early days, but we’ve acknowledged the fact that we need  more capacity in Zimbabwe,” Potgieter said.